Installing a Pool in Richmond Hill: Site Alteration and Enclosure Permits

Richmond Hill's combined pool site alteration and enclosure permit explained: grading plans, fence heights, gates, TRCA, Oak Ridges Moraine and tree rules.

By Stephan Tosevski Published 5 min read
A rectangular inground pool with paver coping and deck, cedar planter boxes with hydrangeas and small trees, and a wood privacy fence
A rectangular inground pool with paver coping and deck, cedar planter boxes with hydrangeas and small trees, and a wood privacy fence. Photo: Mako Construction project.

Richmond Hill handles pools a little differently from Toronto. Instead of a stand-alone fence permit, below-ground and above-ground pools go through a combined Swimming Pool Site Alteration and Enclosure Permit that looks at grading, drainage, zoning, trees and the fence together. That makes the grading plan the centre of the application — and it is why a pool in Richmond Hill should be designed with the whole backyard from day one.

See our pools page for how we plan pool builds and pool landscapes.

The permit: what it covers

The City's Swimming Pool Site Alteration Permit page says property owners must apply for this permit to install below-ground and above-ground pools, and that it ensures the City's zoning, tree preservation, fence and site alteration by-laws are met. Below- and above-ground pools require a combined pool enclosure and site alteration permit.

The grading plan

Applications need a Grading Plan and a Submission Checklist, submitted digitally. The Grading Plan must be prepared by a Professional Engineer or Ontario Land Surveyor, in accordance with Schedule "B" of the Site Alteration By-law, and proposed grading and drainage must conform to the City's Standards and Specifications Manual. The plan also shows the pool enclosure's location and details, and City staff confirm the pool location conforms to zoning.

Why this matters for design: the grading plan fixes where water goes, the elevations of the patio and coping, and the enclosure line. Changing the patio layout, adding a cabana or moving the pool after approval can mean revising the plan. Designing the pool deck, steps, walls, planting and any structures before the engineer or surveyor prepares the plan saves time.

Fees and security

At the time of writing, the City lists a permit fee of $673.06 for site alterations (other than above-ground pools or hot tubs with no grading changes), a $650 landscaping review fee when an existing tree subject to the Tree By-law will be removed or injured, and a $5,000 refundable site alteration security, released after City inspection once deficiencies and obligations are complete. Check the City page for current amounts before you apply.

Enclosure requirements

The City explains that an enclosure is required for any outdoor body of water contained by artificial means where the depth at any point can exceed 0.6 m (1.96 ft), under Chapter 973 of the City Municipal Code. Generally:

  • the enclosure fence must be at least 1.5 m from the water's edge;
  • it ranges in height from 1.2 m to 1.8 m; and
  • gates must be self-closing or self-latching, with a child-proof lock 1.5 m above the pool deck.

Note the 1.5 m distance from the water — larger than Toronto's 1.2 m. It affects how tight a pool can sit to the patio edge, planters and walls. For regular fences, the Fence By-law allows backyard and side yard fences up to 1.8 m and front yard fences up to 1.2 m, with special provisions on corner lots.

Special areas: TRCA, Site Plan Control and the Oak Ridges Moraine

The City notes several situations that add steps:

  • TRCA Regulated Areas. Properties wholly or partly within a Toronto and Region Conservation Authority regulated area may need a TRCA permit before the site alteration permit is issued.
  • Site Plan Control Areas. Residential properties abutting a railway or within 120 m of a shoreline (per the City's by-law schedules) go through site plan approval instead, starting with a pre-submission meeting.
  • Oak Ridges Moraine. Properties within the Moraine need an Oak Ridges Moraine pre-consultation meeting as part of the application, and may need studies such as a Natural Heritage Evaluation and a conformity statement.
  • Heritage and archaeology. Designated heritage properties, or properties adjacent to them, may need a Cultural Heritage Impact Assessment or heritage permit; properties with archaeological potential may need an archaeological assessment.

If any of these apply, add time to the schedule — and find out before you commit to a design.

New subdivisions

The City notes that for new subdivision homeowners, lot grading must be certified by the developer's engineering consultant before a permit is issued. If your home is new, check your lot grading status with your builder first.

Hot tubs and above-ground pools

Hot tubs and temporary above-ground pools that do not alter grading or drainage do not need a Site Alteration Permit, but the City asks owners to contact By-law to make sure enclosure requirements are met. Permanent above-ground pools need a Site Alteration Permit with the same fees as a below-ground pool.

Decks around the pool

Raised decks and pool decks have their own rules. Richmond Hill's deck permit checklist says a building permit is required when a deck is attached to a building, more than 600 mm above average grade, or larger than 10 m². Decks are subject to zoning setbacks, and the checklist notes the Ontario Building Code does not allow decks to be attached to brick veneer.

Locates

Excavation for a pool requires a free utility locate through Ontario Dig Authority, requested at least five business days ahead for a single address. Private lines — power to lights, gas to a heater — need a private locator.

A Richmond Hill pool planning sequence

  1. Confirm whether the property is in a TRCA area, Site Plan Control area, the Oak Ridges Moraine, or heritage-designated.
  2. For new homes, confirm lot grading certification.
  3. Design the pool, deck, enclosure, walls, planting and any cabana together.
  4. Have the grading plan prepared by a P.Eng. or OLS.
  5. Submit the combined site alteration and enclosure permit, plus building permits for decks or structures.
  6. Request locates; protect trees.
  7. Build, install the enclosure, pass inspections, and recover the security deposit.

Common mistakes

  • Treating the grading plan as a formality rather than the design document it is.
  • Placing planters, walls or furniture inside the 1.5 m zone around the water where the fence needs to go.
  • Discovering TRCA, Moraine or heritage requirements after the design is finished.
  • Forgetting that new-subdivision lots need grading certification before a permit.
  • Underestimating the schedule: an engineer or surveyor has to prepare the grading plan before you can apply, so book them early in the design process.

Frequently asked questions

Do I need a permit for a pool in Richmond Hill? Yes. Below-ground and above-ground pools need a combined Swimming Pool Site Alteration and Enclosure Permit.

Who prepares the grading plan? A Professional Engineer or Ontario Land Surveyor.

How far from the pool must the fence be in Richmond Hill? Generally at least 1.5 m from the water's edge, with a height between 1.2 m and 1.8 m.

Does a hot tub need a permit in Richmond Hill? Not a site alteration permit if it does not change grading or drainage, but enclosure requirements still apply — check with By-law.

Is the $5,000 security refundable? Yes, after City inspection and once all deficiencies and obligations under the permit are completed.

Planning a pool in Richmond Hill?

Our Modern Poolhouse & Patio in Toronto & the GTA pairs a wood-clad poolhouse with large-format pavers and frameless glass pool fencing. See our pools page or request a quote.

General information current as of November 2026. Confirm current requirements with the City of Richmond Hill.

Sources

This guide is general information, not legal or engineering advice. Rules and fees change; confirm requirements for your property with your municipality.

About the author

Stephan Tosevski

Stephan Tosevski leads Mako Construction. Mako Construction has built high-end outdoor living spaces across Toronto & the GTA since 2016 — decks, cabanas, pergolas, landscaping, pools, outdoor kitchens, and hot tub and swim spa installations. Fully insured, with permit-ready projects and professional site management from consultation to turnover.

Related guides

See also our Pools service.

Start your project

Plan your project with Mako

Tell us about your property, your timeline and your budget band. We reply within one business day.

Request a Quote