Minor Variances for Backyard Projects in Toronto: The Committee of Adjustment
Minor variance in Toronto explained for backyard projects: when the Committee of Adjustment gets involved, the four tests and the steps. Read the guide.

Most backyard projects in Toronto never go near a hearing room. Some do. If a design needs a structure closer to a lot line, larger or taller than the zoning by-law allows, the route to approval is a minor variance, decided by the City's Committee of Adjustment. This guide explains what a minor variance in Toronto is, how the process works for a backyard project, and how to plan a design so you know early whether you are likely to need one.
It is written for homeowners who are still shaping the plan. If you are weighing a full redesign, our backyard renovation service treats the layout, structures and landscape as one design, which is the stage where zoning questions are cheapest to answer.
What a minor variance in Toronto is
Toronto's zoning by-law sets rules for where buildings and structures can sit on a lot and how big they can be: things like setbacks from lot lines, height, floor area and landscaping. A minor variance is a limited exception to one of those rules.
According to the City of Toronto's Committee of Adjustment page, the Committee has authority under the Planning Act to make decisions on applications to vary zoning rules (minor variance), to divide or adjust property lines (consent), and to extend certain existing uses that do not meet current zoning (legal non-conforming uses).
The City's Participation Handbook describes minor variances as specific relief from particular zoning provisions, where the proposal does not conform exactly but follows the general intent of the by-law. A minor variance does not change the by-law or the Official Plan.
The City also notes that many small building projects do not require an application to the Committee of Adjustment. Whether yours does depends on the exact design and your property's zoning, which is a reason to check early rather than assume.
Which backyard projects can trigger a variance
The Committee of Adjustment page does not list backyard structures by name, so there is no official "list of projects that need a variance." In practice, a variance comes up when a design collides with a zoning provision. Typical collisions for backyard work include:
- Distance to a lot line. A cabana, pool house or large structure placed close to a rear or side boundary.
- Size. An accessory structure that is larger in footprint than the by-law allows for your zone.
- Height. A structure taller than the by-law permits.
These are examples of what to ask about, not Toronto's numbers. The actual limits depend on the zone and the by-law section that applies to your lot, so they must be read for your property.
Zoning is also separate from building permits. Our guide to the Toronto building permit process for backyard projects covers when a permit is needed. A design can need a permit, a variance, both or neither. The City's handbook notes that a zoning review can also identify other approvals required before a building permit is released.
Step 1: Find out exactly which rules the design breaks
A variance request is specific. You are not asking the Committee to approve a project in general; you are asking for relief from named provisions of the zoning by-law.
The City's checklist describes two ways to identify these:
- A zoning review prepared by Toronto Building Division staff. According to the City, the zoning examiner's notice lists all applicable minor variances and other applicable law requirements, and a zoning review is strongly recommended as part of an application.
- A zoning review waiver, prepared by the applicant. It must name the zone, the section of the by-law for which relief is sought and each variance requested. The City warns that an incorrect waiver can cause extensive delays or a refusal, and that an approval based on an incorrect list may mean another application is needed for the missing variances.
A design drawn to scale, with dimensions to each lot line, makes that list far easier to produce.
Step 2: Gather the application material
As published by the City, applications are submitted digitally as PDFs by email. A complete application is required before a hearing is scheduled. According to the City's forms page and checklist, the package includes:
- Form A and Form B. The City states that, effective 1 October 2026, the application form was divided into Form A (Application Form) and Form B (Schedule to the Application Form). Both are required.
- A plan of survey prepared by an Ontario Land Surveyor, according to the checklist.
- Plans, including a site plan and floor plans and elevations where they apply.
- Tree materials. The City requires a tree declaration, current colour photos of the whole front and rear yard (even if there are no trees), photos of by-law protected trees on the site and within 6 m (12 m in ravine and natural feature protected areas), and a site plan showing protected trees and tree protection zones where there are any.
- The fee.
The tree requirement is easy to overlook for a backyard job. If your yard has mature trees or backs onto a ravine, read our guide to building near a protected tree in Toronto before the plans are final.
What the City publishes about fees
As published on the City's page, the fees effective 1 January 2026 for a minor variance include a lower fee for additions and alterations to existing dwellings with three units or less, a higher fee for new residential dwellings with three units or less, and double the regular fee for after-the-fact variances. Fees change, so read the current figure on the City's forms page before budgeting. We have deliberately not repeated the dollar amounts here.
Building first and applying later costs more.
Step 3: Hearing, notice and sign
Once staff confirm an application is complete, it is scheduled for a public hearing. The City's handbook explains that neighbours receive a Public Hearing Notice in the mail, and the applicant receives a sign to post on the property. According to the City, the sign must be visible from the street for at least 10 days before the hearing.
The City strongly recommends talking to neighbours before the hearing. For a backyard project this is sound advice for its own sake: the people most affected by a closer structure or a taller one are the people next door, and they are entitled to comment.
Hearings are public. The City's page says they are held in a hybrid in-person and virtual format, are recorded and broadcast, and that the information submitted becomes part of a public record, including names and contact details. Use an email address you are comfortable having public.
The four tests
The Committee decides under the Planning Act. The City's handbook states that Members consider four tests, and that all four must be met for an application to be approved:
- Is the variance minor? The City explains that this is about impact, not only size. Small numbers do not automatically mean small impact.
- Is it desirable for the appropriate development of the site and neighbouring lands?
- Does it maintain the general intent and purpose of the zoning by-law?
- Does it maintain the general intent and purpose of the Official Plan?
The handbook also says Members focus on the impact of the specific variance requested, not on whether the project is a good idea in general.
Decision and appeals
Members announce their decision at the hearing. According to the City, they may approve in full, approve in part, approve with conditions, or refuse.
On appeals, the City's TLAB page states that since 28 November 2022 only the applicant, the Minister of Municipal Affairs and Housing, specified persons and public bodies, as defined in the Planning Act, may appeal Committee of Adjustment decisions. The handbook gives the appeal period for a minor variance as 20 days from the decision date, after which, if no appeal is filed, the decision is final and binding. The City's page stresses that the time limits are set by law and must be respected.
Ways to reduce the chance you need one
A variance adds time, cost and uncertainty. Many of the cheapest fixes happen at design stage:
- Measure the lot properly. A survey shows the real boundaries and any easements. Drawing from assumptions is how setback surprises happen.
- Test the design against the zoning early. Ask for a zoning review, or have the zoning provisions read for your lot before you fall in love with a layout.
- Size structures to the rules where it costs nothing. A pergola or cabana that is slightly smaller or set slightly further back can sometimes deliver the same use. Our guides to pergola permits in Toronto and cabana and pool house permits cover the permit side of those structures.
- Check drainage and trees at the same time. These are common neighbour concerns and are easier to plan for than to defend.
Questions to ask your designer-builder
- Has the design been drawn to scale with dimensions to every lot line?
- Which zoning provisions does it touch, and has anyone read the by-law for my zone?
- Is there a version of the design that avoids needing a variance, and what would it give up? When a design may need a minor variance, the homeowner applies to the Committee of Adjustment, and we provide guidance along the way. Any time the approval process takes is added to the project timeline.
Frequently asked questions
Is a minor variance the same as a building permit?
No. A building permit is about whether construction meets building code and applicable law. A minor variance is permission to depart from a particular zoning by-law provision. A project can need one, both or neither. The City's handbook notes that a zoning review can identify other approvals needed before a building permit is released.
How do I know if my backyard project needs a minor variance?
You compare the design with the zoning by-law provisions for your property. The City recommends a zoning review by Toronto Building staff, which lists the variances a proposal requires. Without one, the applicant must identify the by-law requirements and sign a waiver taking responsibility for the list. Measured drawings and a survey make either route simpler.
Can my neighbours stop a minor variance?
Neighbours receive notice, can submit comments and can speak at the hearing, and the Committee considers their evidence about impact. Since 28 November 2022, though, third parties generally cannot appeal the Committee's decision to the Toronto Local Appeal Body, according to the City. The Committee itself still decides whether the four tests are met.
Is the process the same in other GTA cities?
No. This guide describes the City of Toronto's process and its published forms and fees. Other municipalities run their own committees of adjustment with their own forms, fees and timelines, even though the Planning Act tests are provincial. Always use the municipality's own information for your property.
Plan your backyard with Mako
If you are planning a backyard project and want zoning questions raised during design rather than after it, request a quote. Bring a survey if you have one, photos of the yard, and a note of any structures you hope to add, and we will talk through the layout and the questions to settle first. This guide is general information and not legal or planning advice.
Sources
- toronto.ca/city-government/planning-development/committee-of-adjustment/
- toronto.ca/city-government/planning-development/committee-of-adjustment/forms-su...
- toronto.ca/city-government/planning-development/committee-of-adjustment/about-th...
- toronto.ca/city-government/planning-development/committee-of-adjustment/appeals/...
- toronto.ca/wp-content/uploads/2026/09/95ab-committee-of-adjustment-participation...
- toronto.ca/wp-content/uploads/2026/09/8dcf-committee-of-adjustment-application-f...
- toronto.ca/wp-content/uploads/2017/12/9361-Committee-of-Adjustment-Checklist-Dig...
This guide is general information, not legal or engineering advice. Rules and fees change; confirm requirements for your property with your municipality.
About the author
Stephan Tosevski
Stephan Tosevski leads Mako Construction. Mako Construction has built high-end outdoor living spaces across Toronto & the GTA since 2016 — decks, cabanas, pergolas, landscaping, pools, outdoor kitchens, and hot tub and swim spa installations. Fully insured, with permit-ready projects and professional site management from consultation to turnover.
Related guides
Guide
Does a Backyard Upgrade Add Value to a Toronto Home?
Backyard renovation ROI in Toronto: what makes an outdoor upgrade add value, which projects tend to pay back in daily use, and the mistakes that cost you.
Guide
Toronto Building Permit Process for Backyard Projects: Steps, Timelines and Inspections
The Toronto building permit process for backyard projects: when a permit is needed, review times and inspections, per the City. Know the steps first.
Guide
Design-Build vs General Contractor: Which Is Right for Your Toronto Backyard?
Design build vs general contractor for a Toronto backyard: how each model works, where they differ, and questions to ask before you hire. See which fits.
Guide
Backyard Drainage Solutions for Toronto Clay Soil
Backyard drainage solutions for Toronto clay soil: grading, downspouts, French drains, swales and rain gardens, plus City rules to check. See what works.
See also our Full Backyard Renovations service.